La Finlande

Impact de la déplétion sur la géopolitique présente, passée et à venir.

Modérateurs : Rod, Modérateurs

Avatar de l’utilisateur
energy_isere
Modérateur
Modérateur
Messages : 89517
Inscription : 24 avr. 2005, 21:26
Localisation : Les JO de 68, c'était la
Contact :

Re: La Finlande

Message par energy_isere » 15 août 2020, 08:57

L'exploitant des 2 réacteurs de Loviisa soumet une demande d'extension de sa licence d'exploitation.
Fortum looks to extend operation of Loviisa plant

13 August 2020

Finnish utility Fortum has begun the environmental impact assessment (EIA) procedure for the operation of the two Loviisa nuclear units beyond their current licences. The two-stage process will take about 18 months to complete.

Image

Loviisa (Image: Fortum)

Loviisa unit 1 began commercial operation in 1977 and is currently licensed to operate until the end of 2027. Unit 2, which entered commercial operation in 1981, is licensed until the end of 2030. Both units are VVER-440 pressurised water reactors.

The EIA will consider two options: continued operation of the plant for a maximum of 20 years beyond the current operating licences, followed by decommissioning; or decommissioning the plant - and its associated low and intermediate level waste disposal facility - at the end of the current licence period.

The first phase of the process will include the preparation by Fortum of the EIA programme, which will set out how the environmental impacts of the options will be assessed. The second phase will include the preparation of the EIA report. The procedure includes public consultations at both stages, with stakeholder feedback gathered nationally and internationally.

Finland's Ministry of Economic Affairs and Employment will act as the coordinating authority for the project, while the Ministry of the Environment will be responsible for international consultation.

Thomas Buddas, deputy director of the Loviisa plant, said the facility is in good technical condition and meets current safety requirements. Information from the EIA will support a possible new licence application, he said.

Four nuclear reactors - at Loviisa and Olkiluoto - provide about 30% of Finland's electricity. A fifth unit - Olikiluoto 3 - is under construction and is currently expected to begin electricity production in 2021. Another unit is planned for construction at Hanhikivi and is expected to begin commercial operation in 2028. Finland's government intends to phase out coal-fired electricity generation by 2029 and last year announced a new energy policy with the objective of achieving carbon neutrality by 2035.

Avatar de l’utilisateur
energy_isere
Modérateur
Modérateur
Messages : 89517
Inscription : 24 avr. 2005, 21:26
Localisation : Les JO de 68, c'était la
Contact :

Re: La Finlande

Message par energy_isere » 28 août 2020, 20:54

C'est sans fin ......
Nouveau contretemps pour l'EPR finlandais, qui a plus de 12 ans de retard

PUBLIÉ LE 28/08/2020 HELSINKI (Reuters)

Le groupe finlandais Teollisuuden Voima Oyj (TVO), opérateur de la centrale nucléaire d'Olkiluoto, a annoncé vendredi un nouveau report de près d'un an de la mise en service du réacteur EPR Olkiluoto-3.

Avec ce report de mars 2021 à février 2022, le réacteur pressurisé EPR d'Olkiluoto, construit par un consortium unissant le français Areva et l'allemand Siemens, accuse désormais plus de douze ans de retard par rapport au calendrier initial.

"Le combustible sera chargé dans le réacteur en mars 2021, cette unité sera connectée au réseau électrique en octobre de la même année et la production régulière d'électricité commencera en février 2022", a dit TVO, en précisant que ce nouveau calendrier avait été avancé par son fournisseur, le consortium franco-allemand Areva-Siemens.

Ce réacteur EPR aurait dû être terminé en 2009 pour un début de la production d'électricité en 2010.
https://www.usinenouvelle.com/article/n ... rd.N997794

Allez l' an prochain ils nous feront bien un treize à la douzaine pour perdre encore un an ........

Avatar de l’utilisateur
energy_isere
Modérateur
Modérateur
Messages : 89517
Inscription : 24 avr. 2005, 21:26
Localisation : Les JO de 68, c'était la
Contact :

Re: La Finlande

Message par energy_isere » 10 déc. 2020, 07:56

Climat: en Finlande, la délicate bataille contre la très polluante tourbe

AFP parue le 10 déc. 2020

Dans une vaste étendue de terre sombre entourée de forêts, le tracteur de Taisto Raussi tire une imposante machine jaune pour collecter la couche de tourbe à la surface: en Finlande, dernier pays de l'UE à utiliser à grande échelle cette énergie polluante, une bataille est engagée pour s'en débarrasser.

Lorsque le septuagénaire s'est installé comme tourbier en 1973 à Sippola (sud-est), "il y avait une crise énergétique en Finlande" et la tourbe est alors venue combler les besoins, raconte-t-il à l'AFP.

"Maintenant, on a l'impression que tout le monde est contre la tourbe, il ne reste plus que quelques personnes qui en vivent", se désole le chef d'entreprise au milieu de son exploitation, grande comme 180 terrains de football et forte de 10 employés.

La récolte partait jadis avant même la fin de l'hiver. Aujourd'hui, de grands monticules de tourbe recouverts de plastique noir - des invendus de l'année dernière - parsèment ses terres.

Autrefois appelée l'"or brun", la tourbe est une matière organique dense qui s'accumule pendant des milliers d'années dans les zones humides et les sols forestiers. Elle couvre près d'un tiers de la surface de la Finlande, un record mondial.

Le pays nordique, de très loin plus grand brûleur de tourbe de l'UE devant l'Irlande et les pays baltes, se divise depuis plusieurs années autour de cette source d'énergie plus polluante que le charbon - à l'impact environnemental considérable.

Selon l'ONU, les tourbières dans le monde stockent plus de carbone que l'ensemble des forêts. Les seules tourbières du nord de l'Europe sont ainsi un plus grand puits de carbone que la forêt amazonienne, selon une récente étude de l'Université de Stockholm.

Lorsque la matière est déterrée et brûlée, elle émet donc d'importantes quantités de CO2.

Si la tourbe est exploitée ailleurs depuis le Moyen-Age, son exploitation en Finlande date de la fin de la Seconde Guerre mondiale.

- Villes contre campagne -

Utilisée essentiellement pour l'industrie du papier et le chauffage collectif, elle couvre 5% des besoins en énergie de la Finlande, soit l'équivalent de 1,5 million de tonnes de pétrole. Mais à elle seule, elle génère 14% des émissions du pays.

La position des parlementaires nationaux - majoritairement favorables à l'élimination progressive de la tourbe comme source d'énergie - alimente désormais le ressentiment entre populations urbaines, à tendance écologiste, et les communautés rurales où le secteur fournit 4.000 emplois directs et le double d'indirects.

La Finlande ambitionne de devenir neutre en carbone d'ici à 2035, mais le gouvernement de centre-gauche s'est engagé à ne réduire que de moitié l'utilisation de la tourbe d'ici 2030, un objectif jugé insuffisant par les associations environnementales.

Mais avec le cours élevé des quotas d'émission européens, le marché pourrait bien accélérer les choses.

"Nous estimons que le secteur de la tourbe combustible sera plus ou moins mort dans dix ans", anticipe Pasi Rantonen, responsable de l'exploitation de la tourbe chez le producteur d'énergie finlandais Vapo, détenu par l'Etat.

La disparition du secteur ne signifiera pas pour autant la fin des dégâts environnementaux.

- "Héritage terrible" -

Pour Tero Mustonen, membre du Groupe d'experts intergouvernemental sur l'évolution du climat (GIEC), le secteur a depuis 75 ans "détruit et mutilé tant de nos rivières, lacs et zones humides", "un héritage environnemental terrible".

Il y a dix ans, l'expert du climat a constaté que les poissons de la rivière Juhajoki, près de son village de Selkie, à 70 kilomètres de la frontière russe, mouraient en masse. Des métaux et autres substances nocives s'échappaient de la tourbière voisine, exploitée par Vapo.

Le scientifique, qui dirige aujourd'hui une association de retour à l'état sauvage baptisée Snowchange, s'est alors battu pour faire fermer la tourbière.

Après de premiers travaux menés par Vapo pour restaurer la zone humide, son association a oeuvré pendant des années pour la faire revivre, de même que les 60 hectares du bassin versant environnant.

Près de 200 espèces d'oiseaux y sont revenues, ainsi que de nombreux poissons.

L'activité de Snowchange s'est depuis étendue sur 23 autres sites de tourbières dégradées à travers le pays - jusqu'au cercle polaire.

L'association souhaite désormais s'occuper de 50.000 km2 de forêts, dont le sol rempli de tourbe a été drainé entre les années 50 et 80 pour stimuler la croissance des arbres, générant là aussi des émissions.

Couvrant un territoire immense, "elles ont le potentiel d'être une solution naturelle pour le climat", souligne M. Mustonen.
https://www.connaissancedesenergies.org ... rbe-201210

Avatar de l’utilisateur
energy_isere
Modérateur
Modérateur
Messages : 89517
Inscription : 24 avr. 2005, 21:26
Localisation : Les JO de 68, c'était la
Contact :

Re: La Finlande

Message par energy_isere » 26 mars 2021, 14:13

Nucléaire : feu vert au chargement du combustible de l'EPR finlandais

AFP parue le 26 mars 2021

L'autorité finlandaise de sûreté nucléaire a annoncé vendredi avoir donné son feu vert au chargement du combustible du réacteur nucléaire EPR d'Olkiluoto 3, une étape permettant son démarrage en vue de la mise en service commerciale prévue en février 2022, avec plus d'une décennie de retard.

"Le chargement du combustible démarrera donc avant la fin du mois de mars 2021", a annoncé de son côté le groupe nucléaire français Areva SA, responsable de ce très long chantier qui a tourné au fiasco industriel et financier. "Le chargement du combustible signifie que Olkiluoto 3 (OL3) est désormais un réacteur nucléaire", s'est félicité l'exploitant TVO dans un communiqué, saluant "l'étape la plus importante dans la mise en service de la centrale jusqu'à présent".

Dans son permis d'autorisation de chargement de l'uranium, l'autorité de sûreté nucléaire finlandaise (STUK) estime que l'EPR "remplit les exigences de sûreté qui ont été fixées et que les procédures d'urgence sont suffisantes pour charger le combustible nucléaire dans le réacteur", a-t-elle annoncé dans un communiqué.

Après ce chargement de combustible, permettant le démarrage du réacteur, TVO va mener une phase de mise en service de "plusieurs mois" durant laquelle il va continuer à tester la centrale, rappelle la STUK. Selon l'autorité, TVO prévoit toujours une mise en service commerciale en février 2022. Ce calendrier avait été communiqué par l'énergéticien en août dernier, lors de l'annonce d'un nouveau retard de plus d'un an pour la production normale d'électricité.

Confié au départ à un consortium entre Areva et l'allemand Siemens, l'EPR finlandais devait initialement être mis en service en 2009 en plus de deux réacteurs existants à Olkiluoto dans le sud-ouest de la Finlande. Mais le chantier lancé en 2005 a connu d'importants retards et surcoûts, qui se traduisent notamment par de lourdes pénalités de retard pour Areva SA.

Issue de l'ancien groupe Areva, dont les activités principales ont par ailleurs donné naissance à Orano et Framatome (filiale d'EDF), Areva SA est une structure dont le but essentiel est d'achever le chantier finlandais.
https://www.connaissancedesenergies.org ... ais-210326

Avatar de l’utilisateur
energy_isere
Modérateur
Modérateur
Messages : 89517
Inscription : 24 avr. 2005, 21:26
Localisation : Les JO de 68, c'était la
Contact :

Re: La Finlande

Message par energy_isere » 31 mars 2021, 01:18

Chargement du combustible dans l' EPR de Finlande :
Fuel loading under way at Finnish EPR

29 March 2021

The loading of fuel assemblies into the Olkiluoto 3 (OL3) EPR in Finland began on 27 March, utility Teollisuuden Voima Oyj (TVO) has announced. The move follows the receipt of a permit from the country's Radiation and Nuclear Safety Authority (STUK) the previous day. The process of loading the fuel assemblies into OL3 is expected to take about one week, TVO said.

Image
Workers at OL3 have already practised loading fuel assemblies into the reactor's core (Image: TVO)

The fuel for OL3 arrived in Olkiluoto in 2018. A total of 241 fuel assemblies manufactured in Framatome's plants in Germany and France will be transferred from storage and loaded into the reactor vessel to constitute the first core.

To carry out the loading operations, an integrated team of about 40 employees from TVO, Areva and Framatome has been formed. It includes around 15 fuel handlers, personnel specialised in fuel handling operations, and four neutronics engineers in charge of monitoring the core during loading.

The loading of fuel will be followed by a commissioning phase lasting several months during which TVO will conduct a new series of hot functional tests to verify the plant's systems work correctly. The previous hot functional test - carried out without nuclear fuel in the reactor - was completed in 2018.

"The most important test is the hot functional test, in which the reactor and turbine island is tested for use," TVO said. "During testing, dozens of separate tests are performed with different pressure and temperature levels."

These tests must be completed before the unit achieves first criticality and commissioning for commercial operation. TVO requires authorisation from STUK before advancing from one commissioning phase to another. TVO was granted an operating licence by the Finnish government for OL3 in March 2019.

"Through the fuel loading, Olkiluoto 3 is now a nuclear power plant, and we are a significant step closer to the realisation of Finland's greatest single act for the climate," said Marjo Mustonen, senior vice president for electricity production at TVO.

OL3 is scheduled to be connected to the grid in October this year, with regular electricity production due to start in February 2022. According to the commissioning programme, the plant will produce 1-3 terawatt-hours (TWh) of electricity with varying power output during the period between grid connection and the start of regular electricity production. Once operating at full capacity, the OL3 plant will produce about 13 TWh of electricity annually and meet about 14% of Finland's electricity demand.
https://www.world-nuclear-news.org/Arti ... innish-EPR

Avatar de l’utilisateur
energy_isere
Modérateur
Modérateur
Messages : 89517
Inscription : 24 avr. 2005, 21:26
Localisation : Les JO de 68, c'était la
Contact :

Re: La Finlande

Message par energy_isere » 17 avr. 2021, 10:17

Neoen sécurise auprès de MEAG le financement du plus grand parc éolien de Finlande (404 MW)

Helsinki et Paris, le 08 avril 2021

• Neoen a finalisé le financement de Mutkalampi qui, avec une puissance de 404 MW, sera
le plus grand parc éolien de Finlande et représentera près de 2% de la production annuelle
du pays

• Ce parc sera également le plus grand actif éolien de Neoen au niveau mondial

• La majorité de l’électricité produite par Mutkalampi sera vendue à Google, Heineken,
Nobian (anciennement Nouryon), Philips et Signify, via 5 corporate PPA de 10 ans, pour
un total de 251 MW

• Le projet est détenu à 100% par Neoen et sa dette senior, sans recours, sera apportée
par MEAG, filiale de Munich Re

• Avec le parc éolien de Hedet (81 MW), la batterie de Yllikkälä (30 MW / 30 MWh) et le parc
de Mutkalampi (404 MW), la Finlande deviendra le troisième pays de Neoen en termes de
puissance installée (515 MW)
Neoen
.............
source communiqué de presse de Neoen
https://www.neoen.com/var/fichiers/neoe ... 210408.pdf

Avatar de l’utilisateur
energy_isere
Modérateur
Modérateur
Messages : 89517
Inscription : 24 avr. 2005, 21:26
Localisation : Les JO de 68, c'était la
Contact :

Re: La Finlande

Message par energy_isere » 08 mai 2021, 13:20

suite de ce post du 1er janv 2019 : http://www.oleocene.org/phpBB3/viewtopi ... 1#p2278031

Le projet de réacteur nucléaire Hanhikivi 1 avec Rosatom prend du retard.
Début de construction maintenant planifié pour l' été 2023.
Fennovoima revises Hanhikivi 1 schedule and costs

28 April 2021

The planned nuclear power plant in Finland is now likely to enter commercial operation a year later and cost up to EUR1 billion (USD1.2 billion) more than previously expected, Fennovoima says in an update to its construction licence application. The company submitted the update today to the Ministry of Economic Affairs and Employment.

Image
he Hanhikivi 1 construction site (Image: Fennovoima)

Fennovoima signed the plant supply contract for Hanhikivi with Rusatom Overseas - Rosatom's nuclear power plant exports subsidiary - in December 2013. Rosatom offered to build a plant using a 1200 MWe AES-2006 VVER under a fixed-price contract. The Hanhikivi project is owned by Fennovoima, in which a 34% stake is held by RAOS Voima Oy, the Finnish subsidiary set up in 2014 by Rosatom for the purpose of buying a share in the company.

The update, Fennovoima said, "describes the material changes and development" that have taken place in the project since the original licence application was submitted on 30 June 2015.

"Since then, the project has progressed and the boundary conditions affecting it have changed," the company informed the ministry. "These changes do not change the basis of the project from the decision-in-principle phase, but they do supplement the information presented in the construction licence application." It noted, "The update does not change the scope of the Hanhikivi 1 project."

The design and licensing work for the Hanhikivi 1 project has progressed well over the past two years, Fennovoima said. However, "Ensuring compliance of the nuclear power plant design and licensing material with the Finnish requirements has caused some delays in the start of construction. On the other hand, the delay at the licensing phase has enabled better preparation for the transition to the construction phase, which is expected to reduce the cost, quality and schedule risks at the construction phase. The delay of approximately five years experienced at the licensing phase is expected to remain unchanged after the transition to the operational phase."

In the update, Fennovoima estimates that it could obtain the construction licence by the summer of next year and that construction of the power plant would begin in the summer of 2023. Commercial operation would begin in 2029, instead of the previously scheduled 2028.

Fennovoima also said the total investment costs of the project have increased to EUR7–7.5 billion, up from the previous estimate of EUR6.5–7 billion. This increase is "mainly due to the five-year delay in obtaining the construction licence and, to a lesser extent, changes in the project's scope of supply."

It noted that, as the plant supply contract with RAOS Project Oy is a fixed-priced contract, the excess additional costs are due to expenses from Fennovoima's own operations and, in particular, expenses from the Fennovoima organisation. "Compensation for the delay from the plant supplier would decrease the project's currently estimated total price," Fennovoima said.

Fennovoima CEO Joachim Specht said "The power plant project will be implemented on the Hanhikivi peninsula in Pyhäjoki, as described in the original application. At this stage, it is essential for both us and the plant supplier to prepare for the future phases of the project, both for the construction and the commissioning of the power plant. Based on the design material, we know that we will have a good nuclear power plant that can be built on the Hanhikivi peninsula, meeting strict Finnish requirements."
https://www.world-nuclear-news.org/Arti ... -and-costs

Avatar de l’utilisateur
energy_isere
Modérateur
Modérateur
Messages : 89517
Inscription : 24 avr. 2005, 21:26
Localisation : Les JO de 68, c'était la
Contact :

Re: La Finlande

Message par energy_isere » 21 août 2021, 00:02

Nucléaire: nouveau retard de trois mois pour l'EPR finlandais

AFP parue le 20 août 2021

La mise en service du réacteur nucléaire EPR en construction par le consortium Areva-Siemens en Finlande a de nouveau été repousée de trois mois, en raison d'une révision de la turbine, a annoncé vendredi son exploitant, le groupe finlandais TVO.

Le démarrage du réacteur OL3 est désormais attendu en janvier 2022, suivi par une première production d'électricité en février et enfin une production régulière en juin, indique TVO dans un communiqué.

La production régulière d'électricité était jusqu'à présent prévue pour mars 2022, selon le précédent calendrier communiqué fin juillet à l'occasion d'un nouveau retard.

"Lors du travail d'inspection de la turbine, le fournisseur a décidé d'étendre la révision à l'ensemble des trois turbines à basse pression afin d'y réaliser de nouvelles inspections", a expliqué TVO vendredi.

Dans le calendrier initial, l'EPR finlandais devait être mis en service en 2009 à la centrale d'Olkiluoto (sud-ouest), mais le chantier lancé en 2005 a connu des retards et surcoûts considérables.

Avec une puissance de 1.650 mégawatts, l'EPR doit fournir près de 15% de l'électricité finlandaise.
https://www.connaissancedesenergies.org ... ais-210820

Avatar de l’utilisateur
energy_isere
Modérateur
Modérateur
Messages : 89517
Inscription : 24 avr. 2005, 21:26
Localisation : Les JO de 68, c'était la
Contact :

Re: La Finlande

Message par energy_isere » 08 déc. 2021, 23:11

EPR finlandais : l'électricien TVO demande l'autorisation de lancer la réaction en chaîne

AFP parue le 08 déc. 2021

L'électricien TVO a annoncé mercredi avoir demandé à l'autorité finlandaise de sûreté l'autorisation pour lancer la réaction en chaîne dans le cœur du réacteur nucléaire EPR d'Olkiluoto 3, construit par le consortium Areva-Siemens et qui accuse déjà plus de dix ans de retard.

TVO, "en collaboration avec le consortium AREVA-Siemens (...), a établi que le projet EPR OL3 a progressé plus rapidement que ce qui avait été communiqué précédemment", a indiqué le Finlandais dans un communiqué. Sur cette base, le groupe a expliqué avoir déposé une demande d'autorisation auprès de l'autorité finlandaise de sûreté nucléaire (STUK) afin de procéder à la divergence et effectuer des tests à faible puissance. "Une fois que STUK aura accordé l'autorisation (...) TVO communiquera ses effets potentiels sur le calendrier de démarrage de la production d'électricité", a également indiqué le groupe.

Selon le dernier plan de marche annoncé en août par TVO, le démarrage du réacteur était attendu en janvier 2022, suivi par une première production d'électricité en février et enfin une production régulière en juin. Dans le calendrier initial, l'EPR finlandais devait être mis en service en 2009 à la centrale d'Olkiluoto (sud-ouest), mais le chantier lancé en 2005 a connu des retards et surcoûts considérables.

Avec une puissance de 1 650 mégawatts, l'EPR d'Olkiluoto 3 doit fournir près de 15% de l'électricité finlandaise. Seuls deux réacteurs EPR sont à ce jour entrés en fonctionnement dans le monde, ceux de la centrale de Taishan en Chine. Deux autres exemplaires sont en chantier en Angleterre.

La France construit pour sa part un exemplaire unique à Flamanville (Manche), qui a connu de nombreux retards et surcoûts. Mais le président Emmanuel Macron a récemment annoncé que le pays allait lancer un nouveau programme nucléaire, sans toutefois préciser le nombre d'exemplaires à ce stade.
https://www.connaissancedesenergies.org ... ine-211208

Avatar de l’utilisateur
energy_isere
Modérateur
Modérateur
Messages : 89517
Inscription : 24 avr. 2005, 21:26
Localisation : Les JO de 68, c'était la
Contact :

Re: La Finlande

Message par energy_isere » 09 déc. 2021, 23:14

Plus gros projet de parc éolien on shore en Finlande avec 69 turbines de 6.6 MW. Total de 455 MW.
Durée de vie de 35 ans !
Finland’s energy transition to accelerate with country’s largest wind power project of 455MW

November 23, 2021 evwind

The 455MW Lestijärvi wind farm with Swedish developer OX2 is due to be installed in 2024. The site will use 69 SG 6.6-170 wind turbines, providing a competitive Levelized Cost of Energy.
When finished the project will produce around 2% of the country’s electricity output. Lestijärvi is the second wind farm signed for the Siemens Gamesa 5.X platform in Finland in 2021. A 35-year full scope service agreement has also been reached.

Siemens Gamesa has struck a 455MW deal with Swedish developer OX2 to supply its leading Siemens Gamesa 5.X platform to the Lestijärvi site for what will be Finland’s largest ever wind farm helping the country to take a giant leap in its energy transition.

The wind project will deploy 69 of the SG 6.6-170 turbines to be installed in 2024 at the site in Central Ostrobothnia. The wind turbines are equipped with a 170-meter rotor and 6.6 MW generator providing one of the lowest Levelized Cost of Energy (LCoE) in the industry.

This is the second Finnish site that will use the Siemens Gamesa 5.X following an 81MW deal signed for the SG 6.6-155 variant in early 2021. Lestijärvi will also be the largest ever wind farm in the country by installed capacity and when completed its annual energy production will be about 1.3 terawatt hours, equivalent to around two percent of Finland’s total electricity production.

The wind farm will also be covered by a 35-year full scope service agreement assuring the turbines operate at their maximum capacity over their lifetime. A total of 64 turbines will sit on 155-meter towers, and the other five will use 145-meter towers.
...................
https://www.evwind.es/2021/11/23/finlan ... 55mw/83423

Avatar de l’utilisateur
energy_isere
Modérateur
Modérateur
Messages : 89517
Inscription : 24 avr. 2005, 21:26
Localisation : Les JO de 68, c'était la
Contact :

Re: La Finlande

Message par energy_isere » 16 déc. 2021, 21:07

Nucléaire : l'EPR finlandais autorisé à démarrer par l'autorité de sûreté

AFP le 16 déc. 2021

L'autorité finlandaise de sûreté a donné son autorisation pour démarrer le réacteur nucléaire EPR d'Olkiluoto 3 construit par le consortium franco-allemand Areva-Siemens, a annoncé jeudi l'exploitant finlandais de la centrale, qui vise une production commerciale en juin.


Au terme d'un chantier qui accuse près de douze ans de retard sur le calendrier initial, le Stuk a accordé "l'autorisation de procéder à la divergence et effectuer des tests à faible puissance" avec un premier démarrage au cours du mois de décembre, a annoncé le producteur d'électricité TVO dans un communiqué.

L'exploitant de la centrale d'Olkiluoto, située dans le sud-ouest de la Finlande, table désormais sur une première production d'électricité fin janvier et une production régulière en juin. "La réaction nucléaire dans le réacteur OL3 va être déclenchée pour la première fois au cours du mois de décembre", précise TVO. Selon le régulateur nucléaire finlandais, les tests menés ces derniers temps "démontrent que le réacteur fonctionne comme prévu", souligne le groupe. Areva s'est de son côté réjoui dans un communiqué "du franchissement de cette étape clé".

Le démarrage, autorisé à faible puissance, se fera par étapes encore soumises à des autorisations du régulateur pour passer à 5%, puis 30%, puis 60% de la capacité de 1 650 mégawatts du réacteur.

Olkiluoto-3, qui s'ajoute à une centrale comportant deux réacteurs en opération, est le premier chantier d'un réacteur nucléaire à avoir été commandé en Europe après la catastrophe de Tchernobyl en 1986.

Le fiasco de sa construction, lancée en 2005 et qui devait initialement être terminée en 2009, a entraîné des pertes considérables pour Areva et terni l'image de l'EPR, censé incarner la renaissance du nucléaire. Deux d'entre eux ont déjà été lancés en Chine et un autre est en construction à Flamanville, dans le nord-ouest de la France, là aussi un chantier avec des nombreux retards et problèmes.
https://www.connaissancedesenergies.org ... ete-211216

Avatar de l’utilisateur
energy_isere
Modérateur
Modérateur
Messages : 89517
Inscription : 24 avr. 2005, 21:26
Localisation : Les JO de 68, c'était la
Contact :

Re: La Finlande

Message par energy_isere » 21 déc. 2021, 19:06

Nucléaire : l'EPR finlandais a démarré après 16 ans de chantier et 12 ans de retard

AFP le 21 déc. 2021

Après seize ans de chantier et douze ans de retard sur la date de mise en service prévue initialement, le réacteur nucléaire EPR construit par le français Areva en Finlande a démarré cette nuit pour la première fois, a annoncé mardi l'exploitant de la centrale.

Après la première réaction en chaîne à 03h22 locales (01h22 GMT) à l'intérieur du réacteur, la production d'électricité doit commencer à environ 30% de la puissance lors du raccordement au réseau en janvier, avant une mise en service normale en juin, indique l'énergéticien finlandais TVO dans un communiqué.

"Le moment du démarrage a été historique. La dernière fois qu'un réacteur a été lancé en Finlande remonte à il y a plus de 40 ans, et même en Europe cet évènement remonte à environ 15 ans", souligne l'exploitant de la centrale d'Olkiluoto, en référence au lancement d'un réacteur en Roumanie en 2007.

Au terme de ce chantier lancé en 2005 dans le sud-ouest de la Finlande, devenu pour Areva un chemin de croix miné par les retards et les dérives financières, l'EPR d'Olkiluoto va devenir le plus puissant réacteur en opération en Europe.

Avec une capacité de production de 1 650 mégawatts, il doit fournir environ 15% de la consommation du pays nordique. "Ce moment restera pour toujours comme la démonstration de la persistance de notre travail pour mettre en service notre nouveau réacteur", a déclaré Marjo Mustonen, vice-président de TVO, saluant "la plus grande contribution de la Finlande pour le climat".

Après le chargement du combustible dans le réacteur en mars, le gendarme finlandais du nucléaire avait autorisé le démarrage du réacteur la semaine dernière. Conçu pour relancer l'énergie nucléaire après la catastrophe de Tchernobyl en 1986, notamment grâce à une considérable structure de béton et des améliorations de sûreté, l'EPR a rencontré d'importants problèmes de construction, notamment en Finlande mais aussi à Flamanville en France.

Enfin la « renaissance » ?

À Olkiluoto, ces difficultés ont entraîné de longues et vives tensions entre TVO, Areva et l'autorité finlandaise du nucléaire, la Stuk. TVO avait signé en mars 2019 un accord pour mettre fin au contentieux, prévoyant qu'une indemnisation de 450 millions d'euros lui soit versée. Le Covid-19 avait à son tour provoqué de nouveaux retards sur le chantier finlandais, sur un site où deux anciens réacteurs sont déjà en opération.

Seuls deux réacteurs EPR étaient jusqu'à présent entrés en fonctionnement dans le monde, ceux de la centrale de Taishan en Chine. Leur construction avait débuté après celle d'Olkiluoto-3, premier réacteur nucléaire à avoir été commandé dans l'Union européenne depuis Tchernobyl. Le réacteur numéro 1 de cette centrale située près de Hong Kong est toutefois à l'arrêt depuis juillet après un incident, qualifié de "courant" par Pékin.
...............
https://www.connaissancedesenergies.org ... ard-211221

Avatar de l’utilisateur
energy_isere
Modérateur
Modérateur
Messages : 89517
Inscription : 24 avr. 2005, 21:26
Localisation : Les JO de 68, c'était la
Contact :

Re: La Finlande

Message par energy_isere » 04 févr. 2022, 01:14

Nucléaire: nouveau retard pour la production d'électricité de l'EPR finlandais

AFP le 03 févr. 2022

L'électricien finlandais TVO a annoncé jeudi reporter d'un mois la production d'électricité du réacteur nucléaire EPR d'Olkiluoto-3, construit par le consortium Areva-Siemens, douze ans après la date de mise en service prévue initialement.

"Le début de la production d'électricité est reporté car la nécessité de faire des modifications a été observée pendant la phase de production test" lancée fin décembre, a prévenu l'énergéticien dans un communiqué.

La production d'électricité doit commencer fin février, au lieu de janvier comme annoncé précédemment. Une mise en service normale aura lieu en juillet 2022 alors que TVO tablait auparavant sur juin.

"Au cours de la phase d'essai de production de l'unité de production OL3, il a été observé que des modifications devaient être apportées à l'automatisation de l'unité concernant les fonctions de contrôle", a précisé TVO.

Des mesures correctives sont engagées, a-t-il ajouté.

Au terme de ce chantier lancé en 2005 dans le sud-ouest de la Finlande, devenu pour Areva un chemin de croix miné par les retards et les dérives financières, l'EPR finlandais va devenir le plus puissant réacteur en opération en Europe.

Avec une capacité de production de 1.650 mégawatts, il doit fournir environ 15% de la consommation du pays nordique.

Avant Olkiluoto-3, seuls deux réacteurs EPR sont entrés en fonctionnement dans le monde, ceux de la centrale de Taishan en Chine.
https://www.connaissancedesenergies.org ... ais-220203

Avatar de l’utilisateur
mobar
Hydrogène
Hydrogène
Messages : 18141
Inscription : 02 mai 2006, 12:10
Localisation : PR des Vosges du Nord

Re: La Finlande

Message par mobar » 21 févr. 2022, 10:25

"Les modifications et les tests prennent plus de temps que prévu et nous devons en conséquence actualiser le calendrier", a expliqué TVO. Une mise en service normale est attendue en juillet 2022.
https://www.latribune.fr/entreprises-fi ... 04000.html
16 ans de construction dont plus de 12 ans de retard et un cout initial multiplié par 4!

Mais, et c'est rassurant, les surcouts ne seront pas entièrement payés par Framatome filiale d'EDF, le contribuable français participera pour effacer l'ardoise! :mrgreen:
Mais Le Monde rapporte que les nouveaux retards accumulés obligent Areva à verser 400 millions d'euros supplémentaires dans le cadre de l'accord de 2019. Plus inquiétant, le quotidien, qui a consulté un document confidentiel adressé au conseil social et économique (CSE) du groupe, révèle qu'un nouvel accord serait dans les tuyaux, faisant gonfler la douloureuse à 600 millions d'euros.

Areva n'aurait alors qu'une solution pour se remettre à flot : céder 16 % de sa participation dans Orano, une multinationale française spécialisée dans les métiers du combustible nucléaire. Une opération qui se ferait au frais du contribuable, précise Le Monde. C'est pourquoi l'État se retrouve dans l'obligation d'effacer l'ardoise de son fleuron.
https://youtu.be/0pK01iKwb1U
« Ne doutez jamais qu'un petit groupe de personnes bien informées et impliquées puisse changer le monde, en fait, ce n'est jamais que comme cela que le monde a changé »

Avatar de l’utilisateur
energy_isere
Modérateur
Modérateur
Messages : 89517
Inscription : 24 avr. 2005, 21:26
Localisation : Les JO de 68, c'était la
Contact :

Re: La Finlande

Message par energy_isere » 26 févr. 2022, 15:40

suite de ce post du 8 mai 2021 viewtopic.php?p=2318749#p2318749

Le projet de centrale nucléaire de Hanhikivi' avec les Russes est maintenant fortement compromis.
Finland questions Hanhikivi's prospects amid Ukraine conflict
25 February 2022

Fennovoima says that the "Russian invasion of Ukraine, and the counter measures by EU and western countries as a consequence" pose a "major risk" to the future of the nuclear power plant project.

Finland’s Minister for Economic Affairs Mika Lintila told the country’s parliament that he would not be granting a building permit for the Hanhikivi nuclear plant as things stand.

"It's quite clear that as a consequence of this conflict this project will at least be significantly delayed," Lintilä told the STT newswire on Thursday.

Fennovoima, the company behind the planned nuclear power plant which will have a Russian reactor and is one third owned by a Finnish subsidiary of Russia’s Rosatom, said it "acknowledges that the ongoing conflict situation may have impacts on the Hanhikivi 1 project".

It said the "Russian invasion of Ukraine, and the counter measures by EU and western countries as a consequence, pose a major risk for the Hanhikivi 1 project.

"We are very sad about the developments and the situation in Ukraine. There are a lot of people close to our employees in the area and our thoughts are with them."

According to Finland’s STT news agency, Fennovoima is now waiting to hear what sanctions the EU will impose on Russia before speculating on the project's future.

Last month licensing work for the Hanhikivi 1 nuclear power plant was said to have reached the “homestretch” with Fennovoima expecting to submit its final licensing materials to the Radiation and Nuclear Safety Authority by the end of February, with the goal of gaining a construction licence this year.

Fennovoima signed the plant supply contract for Hanhikivi with Rusatom Overseas - Rosatom's nuclear power plant exports subsidiary - in December 2013. Rosatom offered to build a plant using a 1200 MWe AES-2006 VVER under a fixed-price contract. The Hanhikivi project is owned by Fennovoima, in which a 34% stake is held by RAOS Voima Oy, the Finnish subsidiary set up in 2014 by Rosatom for the purpose of buying a share in the company.

Fennovoima submitted its 250-page construction licence application to Finland's Ministry of Employment and the Economy for the Hanhikivi plant in June 2015. The government's decision to issue a construction licence would require a positive assessment of the application by STUK.
https://www.world-nuclear-news.org/Arti ... at-major-r

Répondre